Manufacture and supply of Hot Reheat Bend Pipes at Matla Power Station (Once-off)
ESKOM
State-owned company · Tender (request for bid) · Mpumalanga · Tender no. E3843GXMPMAT
3 days left
Closes: Tuesday, 1 December 2026 at 10:00 SAST
Requirements, and how we know them
- At least 70% on functionality (Read from official document)
- CIDB grade (Not confirmed)
- Tender documents (Not confirmed)
- CIDB registration (General guidance)
- CSD registration (General guidance)
- Valid tax compliance status (General guidance)
- Standard SBD forms (General guidance)
Find it on eTenders: search for E3843GXMPMAT
Official documents
- BILL OF QUANTITY - Copy.pdf
- ENVIRONMENTAL REQUIREMENTS - Copy.pdf
- Health and Safety requiments for Low risk - Copy.pdf
- Scope for manufacture and supply of hot reheat bends_MP_YM - Copy.pdf
- SDL&I Requirements - Copy.pdf
- INVITATION TO TENDER BEND PIPES - Copy.pdf
- NEC - Copy.pdf
- List of Tender Returnables-Manufacture and Supply of Hot Reheat Bends at Matla.xlsx
- 240-68099512 (Rev 9) Form A Tender & Contract Quality Requirements- Manufacture and Supply of Hot Reheat Bends at Matla .docx
- Health and Safety requiments for Low risk - Copy.pdf
- Tender Questions and Answers E3843GXMPMAT.pdf
- NEC3 Supply Contract (SC3) for Manufacture and supply of Hot Reheat Bends at Matla Power Station (Once – off) (1).pdf
- Technical criteria for once off procurement of Hot reheat bends_YM-1.pdf
Official contact
Katlego Tsatsane · tsatsak@eskom.co.za · 017-612-9156
Before you submit
- Sign every SBD form
Usually SBD 1, SBD 3.1, SBD 4 and SBD 6.1, as issued in this tender pack. One unsigned form can disqualify the bid; the signatory must be authorised to sign for the business. - Tax compliance status valid on the closing date
Check it on SARS eFiling before 01 Dec 2026. A status that lapses before closing can cost you the award. - CSD profile compliant, details matching
Your CSD record should show as compliant, with the same name, registration number and directors as CIPC, SARS and your B-BBEE documents. - Proof for every point you claim
Your B-BBEE affidavit or certificate, and anything else the SBD 6.1 asks for, must support the specific-goal points you claim. - Reach 70% on functionality
Bids below the threshold aren't scored on price. Include every CV, reference letter and method statement the scoring table asks for. - The buyer's pricing schedule, complete
Use the schedule exactly as issued, fill in every line, and check whether prices must include VAT. - Every returnable schedule
List the returnable documents from the tender pack itself and tick them off, rather than relying on your last bid. - Submit a day early
Late bids aren't considered, even by a minute. Aim to submit by 30 Nov 2026, and check the address or upload method twice.